The School Board approves creation of a long-range facility planning process to identify enrollment projections, building capacity calculations, community growth plans and to collect data.
A steering committee of administrators is created to gather input from stakeholders to help make a final recommendation to the superintendent
March-Aug. 2019 The Steering Committee reviewed and collected enrollment projections, building capacities, community growth plans and other important data.
June-Sept. 2019 Interviews were conducted with principals, department leaders, choice program providers and other internal stakeholders to determine current and projected use for student learning.
A task force of staff and community members (35+) is created to review enrollment projections, building capacity calculations, community growth plans and collect data in order to provide input on construction options.
Hold focus groups to gather input from advisory groups, school staff and city decision-makers.
Explore financing options to help fund growth needs.
Finalize secondary and district site construction options; finalize elementary construction options.
May-June 2020:Hold community input sessions to review the construction options and provide feedback to help the steering committee finalize a recommendation for the superintendent.
Potential bond referendum election.