Admin

Secondary - New High School

Information Sheet

Secondary Plan

Adding a Fourth High School

This plan would make the student population at each high school approximately the same size and would match middle school students to their high school. This is known as a middle school feeder system. Additional construction and renovations will take place at the district’s alternative high school, district service sites and all middle schools. 

The plans listed here are simply a snapshot in time during our facility planning process. All costs and projects are subject to change.
The information presented here was revised:
  • Feb. 20, 2020

High School

Projects

New High School

  • Construction of a new high school

East Ridge High School

  • No infrastructure changes

Park High School

  • Construction of a new cafeteria and kitchen
  • Renovation of existing spaces and addition of three Career and Technical Education (CTE) and Science, Technology, Engineering and Math (STEM) spaces
  • Construction of new locker rooms
  • Renovation of girls locker room into the new band room
  • Remodel to create a student services area (counseling, health, special education)
  • Renovation of the courtyard into an online learning space
  • Remodel of the auditorium and music wing (including audio/visual and lighting)
  • Remodel of the media center and computer labs
  • Construction of additional parking (includes approximately 90 new spaces)
  • Air conditioning for the fieldhouse
  • Artificial turf for the multipurpose field

Woodbury High School

  • Renovation of the kitchen space into three additional science classrooms
  • Construction of a new cafeteria and kitchen
  • Construction of a secure entryway and front office
  • Renovation of the cafeteria into an online learning space
  • Auditorium upgrades for audio/video and lighting
  • Renovation and expansion of the media center
  • Remodel of the special education and student services center
  • Replacement of all flooring
  • Construction and redesign of additional parking (includes approximately 200 new spaces)
  • Air conditioning for the fieldhouse
  • Artificial turf for the multipurpose field

 


Alternative High School

Projects

South Washington Alternative High School

  • Renovation of existing district building into new alternative high school site
  • Renovation of Career and Technical Education (CTE) and Science, Technology, Engineering and Math (STEM) spaces

Middle School

Projects

Cottage Grove Middle School

  • Construction of a secure entryway and front office
  • Renovation of the special education and student services area
  • Expansion of the cafetorium
  • Air conditioning for the gymnasium

Lake Middle School

  • Construction of a secure entryway and front office
  • Renovation of special education and student services area
  • Expansion of the cafetorium
  • Air conditioning for the gymnasium

Oltman Middle School

  • Construction of a 300 seat addition

Woodbury Middle School

  • Construction of a secure entryway and front office
  • Air conditioning for the gymnasium

District Sites

Projects

Transportation




  • Retain the existing transportation site for standard school buses and maintenance
  • Construction of a new site for maintenance (buildings, grounds, carpentry, etc.), vans and special education buses
    • New site to be determined

District Services Center

  • Renovation of the District Services Center for administration use 

Total

$424,788,953

  • Includes high school, alternative high school, middle school and district site projects
  • Middle School: Capacity increase from 5,082 to 5,382
  • High School: Capacity increase from 5,995 to 7,795
  • Alternative High School: Capacity increase from 120 to 300