Elementary - Renovations and Additions

Information Sheet

Elementary Plan

Renovations and Additions: Repurpose Two Schools

This plan accommodates growth through renovations and additions at school sites with the greatest limits on space for students. Two elementary school sites would be repurposed for other uses.

Please note that school sites to be repurposed have not yet been identified at this point in the process.

The plans listed here are simply a snapshot in time during our facility planning process. All costs and projects are subject to change.
The information presented here was revised:
  • Feb. 20, 2020

Elementary Schools

Projects

Bailey Elementary School

  • Construction of a new site addition for Pre-K and kindergarten
  • Construction of two new special education rooms
  • Construction and redesign for additional parking (includes approximately 50 new spaces)

Cottage Grove Elementary School

  • Construction of a new fifth grade wing and two music rooms
  • Expansion of the cafeteria
  • Construction and redesign for additional parking (includes approximately 200 new spaces)

Crestview Elementary School

  • Construction of new bathrooms and renovation of existing bathrooms

Grey Cloud Elementary School

  • Construction of new site addition for Pre-K and kindergarten 
  • Construction of additional parking (includes approximately 60 new spaces)

Hillside Elementary School

  • Construction of new bathrooms and renovation of existing bathrooms

Pine Hill Elementary School

  • Construction of a 200 seat addition 
  • Construction of new bathrooms and renovation of existing bathrooms

Pullman Elementary School

  • Construction of a 120 seat addition
  • Construction of new bathrooms and renovation of existing bathrooms

Red Rock Elementary School

  • Construction of a new fifth grade wing and two music rooms
  • Expansion of the cafeteria

Royal Oaks Elementary School

  • Construction of four new kindergarten rooms
  • Construction of new bathrooms and renovation of existing bathrooms

Woodbury Elementary School

  • Renovation of existing bathrooms

No Infrastructure Changes

Armstrong Elementary

Liberty Ridge Elementary

Middleton Elementary

Newport Elementary

Nuevas Fronteras Spanish Immersion

Valley Crossing Elementary

Total

$77,144,149

  • Elementary School: Capacity increase from 10,116 to 10,435

Modernize 1960’s Era Elementary Schools

Projects

Armstrong Elementary School *

Crestview Elementary School

Hillside Elementary School

Pullman Elementary School

Pine Hill Elementary School

Royal Oaks Elementary School

Woodbury Elementary School

  • Construction of new gym (does not apply to Armstrong Elementary)
  • Renovation of existing gym into collaborative spaces (does not apply to Armstrong Elementary)
  • *Armstrong Elementary: Construction of a new media center and renovation of existing media center into a collaborative space

Modernize 1990’s Era Elementary Schools

Projects

Bailey Elementary School

Grey Cloud Elementary School

Middleton Elementary School

  • Construction of a new cafeteria and kitchen
  • Renovation of kitchen into two music rooms
  • Renovation of computer labs into two special education rooms

Total

$81,075,897

  • Modernization

Total

$158,220,046

  • Modernization + Renovations and Additions: Repurpose Two Schools