Construction Update - May 2026
Construction Update - May 2026
Here are a few Spring 2026 highlights of the ongoing construction projects taking place across the district through two voter-approved bond questions, allowing SoWashCo Schools to begin construction projects at 15 schools over the course of 5 years.
Park High School
- Freezer and cooler flooring were installed
- Concrete work at new entrance has begun
- Kitchen equipment installation is scheduled to start this week
- Storm shutters to be powered up this week

Woodbury High School
- Sheet rock and Curtain walls are in process in Area A
- Deck painting has begun in Area B
- Duct work, rain leader, block work, brick, and roofers have all started in kitchen
- Locker room demo is complete with pour back scheduled for this week

East Ridge High School
- Stoops have been poured around the addition in Area T
- Paint, ceiling and lighting are all in process in Area Q
- Several slabs of concrete have been poured

Oltman Middle School
- Terrazzo, soffits, finishing and tile is all in process in Area C
- Finishes and technology in process in Area D
- Cafeteria Curtain wall has been installed
- Elevator installation is in process

Woodbury Middle School
- Bus gates have been installed
- Prepping for next phase of construction to start later this month
- Irrigation startup is complete

Cottage Grove Middle School
- Drywall returns at windows has started
- Countertop installation is complete
- Vestibule doors have been installed
- Pool Office door and pool egress door work has resumed

Lake Middle School
- Countertop and sink installation is complete
- Pool office and egress door work is in process
- Floor prep is scheduled

