Construction Update - May 2026

Construction Update - May 2026

Here are a few Spring 2026 highlights of the ongoing construction projects taking place across the district through two voter-approved bond questions, allowing SoWashCo Schools to begin construction projects at 15 schools over the course of 5 years.

Park High School 

  • Freezer and cooler flooring were installed
  • Concrete work at new entrance has begun
  • Kitchen equipment installation is scheduled to start this week
  • Storm shutters to be powered up this week
construction site at park high school

Woodbury High School 

  • Sheet rock and Curtain walls are in process in Area A
  • Deck painting has begun in Area B
  • Duct work, rain leader, block work, brick, and roofers have all started in kitchen
  • Locker room demo is complete with pour back scheduled for this week
A JLG lift is in the foreground next to concrete stairs, while the background shows a construction site with exposed ceilings, windows, and workers.

East Ridge High School 

  • Stoops have been poured around the addition in Area T
  • Paint, ceiling and lighting are all in process in Area Q
  • Several slabs of concrete have been poured
A group of construction workers in hard hats and safety vests stand on a wooden platform overlooking a partially constructed building with exposed steel beams and brick walls.

Oltman Middle School 

  • Terrazzo, soffits, finishing and tile is all in process in Area C
  • Finishes and technology in process in Area D
  • Cafeteria Curtain wall has been installed
  • Elevator installation is in process
windows outside of oltman middle school

Woodbury Middle School  

  • Bus gates have been installed
  • Prepping for next phase of construction to start later this month
  • Irrigation startup is complete
A modern gymnasium with a gray floor marked with lines in the foreground and a blue wall with a large white "W" logo in the background.

Cottage Grove Middle School

  • Drywall returns at windows has started
  • Countertop installation is complete
  • Vestibule doors have been installed
  • Pool Office door and pool egress door work has resumed
Gray double doors with glass panels are in the foreground, while a construction area with a ladder is visible through a glass partition in the background.

Lake Middle School

  • Countertop and sink installation is complete
  • Pool office and egress door work is in process
  • Floor prep is scheduled 
A U-shaped counter with cabinets is in the foreground, while construction workers and ladders are visible through a large window in the background.