Construction Update - May 2025
Construction Update - May 2025
Here are a few Spring 2025 highlights of the ongoing construction projects taking place across the district through two voter-approved bond questions, allowing SoWashCo Schools to begin construction projects at 15 schools over the course of 5 years.
Park High School
- Installation of storm sewer structures and piping began
- Prepared a temporary fence to be installed between Park High School and Crestview Elementary
- Demolition of the lecture hall began
- Next Steps: Additional interior demolition, loading dock canopy to be removed, site grading and utility installation
Woodbury High School
- Pool utilities disconnected
- Demolition of the new trainer room/temporary egress began
- Next Steps: Temporary fence arriving, temporary pool wall and demolition, the administration office will temporarily move
East Ridge High School
- Utility work began
- Removed trees, shrubs, stumps and rubbish from the construction site
- Old boilers were removed and new boilers were installed
- Next Steps: Interior demolition will begin
Oltman Middle School
- Foundation walls were poured
- Next Steps: Temporary walls to be installed in the cafeteria and locker bay in Area D, additional footings and foundations to be poured
- Please Note: The parent drop-off road will be shut down after school ends on June 5; the Activities entrance (Door 30) will be shut down for the summer
Woodbury Middle School
- The new bus lane road began and is scheduled to be completed by mid-summer
- Pool deck demolition and infill began for the new multipurpose room
- The fiber line was moved
- Wrestling room and garage demolition began
- Next Steps: Grading, roadwork, interior demolition, continued infill and concrete slab over will be installed over the pool
.
Cottage Grove Middle School
- Site fencing to be installed mid-July
Lake Middle School
- Site fencing to be installed mid-July