Construction Update - May 2025

Construction Update - May 2025

Here are a few Spring 2025 highlights of the ongoing construction projects taking place across the district through two voter-approved bond questions, allowing SoWashCo Schools to begin construction projects at 15 schools over the course of 5 years.

 

Park High School 

  • Installation of storm sewer structures and piping began
  • Prepared a temporary fence to be installed between Park High School and Crestview Elementary
  • Demolition of the lecture hall began
  • Next Steps: Additional interior demolition, loading dock canopy to be removed, site grading and utility installation

rubble     A person in a yellow vest standing next to a metal structure

Woodbury High School 

  • Pool utilities disconnected
  • Demolition of the new trainer room/temporary egress began
  • Next Steps: Temporary fence arriving, temporary pool wall and demolition, the administration office will temporarily move 

A construction site with many pipes  A construction site with many pipes

East Ridge High School 

  • Utility work began
  • Removed trees, shrubs, stumps and rubbish from the construction site
  • Old boilers were removed and new boilers were installed
  • Next Steps: Interior demolition will begin

A building on the side of a road  A road with a building

Oltman Middle School 

  • Foundation walls were poured
  • Next Steps: Temporary walls to be installed in the cafeteria and  locker bay in Area D, additional footings and foundations to be poured
  • Please Note: The parent drop-off road will be shut down after school ends on June 5; the Activities entrance (Door 30) will be shut down for the summer

A group of people working on a construction site A construction site with a building and a road

Woodbury Middle School  

  • The new bus lane road began and is scheduled to be completed by mid-summer
  • Pool deck demolition and infill began for the new multipurpose room
  • The fiber line was moved 
  • Wrestling room and garage demolition began
  • Next Steps: Grading, roadwork, interior demolition, continued infill and concrete slab over will be installed over the pool

A yellow construction vehicle on dirt. A construction site with many pipes

Cottage Grove Middle School

  • Site fencing to be installed mid-July

Lake Middle School

  • Site fencing to be installed mid-July