Construction Update - July 2025

Construction Update - July 2025

Here are a few Spring 2025 highlights of the ongoing construction projects taking place across the district through two voter-approved bond questions, allowing SoWashCo Schools to begin construction projects at 15 schools over the course of 5 years.

Park High School 

  • Road and utility work in between Crestview and Park are in process
  • First lift of the asphalt is scheduled for early August
  • Lecture hall windows are being installed
  • Concrete infills in process
  • Framing in process
  • New footings for addition in process
  • Carpet completed in AC entrance
  • Power Panel shut off in Area H, Area B complete, Area K to complete this week

Woodbury High School 

  • Temporary egress doors to be installed end of July
  • Temp walls have been completed
  • Administrative area demolition is in process and on track
  • Excavation for new addition footings is in process
  • Fiber splice is tentatively scheduled for 8/12

 


 

East Ridge High School 

  • Framing in the new office area and Area B is complete
  • Framing in Area B has been completed, frames and sheetrock installed
  • New Boiler work in process and on track 
  • First lift for parking lot scheduled for early August

A road with a building and trees

AI-generated content may be incorrect.

Oltman Middle School 

  • The temporary wall in the cafeteria was completed and will stay in place until the new cafeteria is completed
  • Kitchen temporary wall is up, finishes and fixtures have been installed, sink to be installed soon
  • Temporary wall in locker bay completed
  • Area C/ D was backfilled
  • Masonry has started on-site 
  • Foundation pour started at the cafeteria
  • Demolition at Area C/ D complete

 

 A group of people working on a construction site

AI-generated content may be incorrect.


Woodbury Middle School  

  • The new bus lane road first lift was completed last week
  • New sidewalk around retention area is complete
  • Bleacher demolition in the former pool is underway 
  • Wrestling room and garage flooring concrete infills are scheduled 
  • Site concrete has been scheduled 

 

A yellow construction vehicle on dirt

AI-generated content may be incorrect.

Cottage Grove Middle School

  • Greeter's desk has been moved
  • Pool office area work to start on 7/22

Lake Middle School

  • Greeter's desk has been moved
  • Pool office area work to start on 7/22