Construction Update - July 2025
Construction Update - July 2025
Here are a few Spring 2025 highlights of the ongoing construction projects taking place across the district through two voter-approved bond questions, allowing SoWashCo Schools to begin construction projects at 15 schools over the course of 5 years.
Park High School
- Road and utility work in between Crestview and Park are in process
- First lift of the asphalt is scheduled for early August
- Lecture hall windows are being installed
- Concrete infills in process
- Framing in process
- New footings for addition in process
- Carpet completed in AC entrance
- Power Panel shut off in Area H, Area B complete, Area K to complete this week
Woodbury High School
- Temporary egress doors to be installed end of July
- Temp walls have been completed
- Administrative area demolition is in process and on track
- Excavation for new addition footings is in process
- Fiber splice is tentatively scheduled for 8/12
East Ridge High School
- Framing in the new office area and Area B is complete
- Framing in Area B has been completed, frames and sheetrock installed
- New Boiler work in process and on track
- First lift for parking lot scheduled for early August
Oltman Middle School
- The temporary wall in the cafeteria was completed and will stay in place until the new cafeteria is completed
- Kitchen temporary wall is up, finishes and fixtures have been installed, sink to be installed soon
- Temporary wall in locker bay completed
- Area C/ D was backfilled
- Masonry has started on-site
- Foundation pour started at the cafeteria
- Demolition at Area C/ D complete
Woodbury Middle School
- The new bus lane road first lift was completed last week
- New sidewalk around retention area is complete
- Bleacher demolition in the former pool is underway
- Wrestling room and garage flooring concrete infills are scheduled
- Site concrete has been scheduled
Cottage Grove Middle School
- Greeter's desk has been moved
- Pool office area work to start on 7/22
Lake Middle School
- Greeter's desk has been moved
- Pool office area work to start on 7/22