Construction Update - June 2025

Construction Update - June 2025

Here are a few Spring 2025 highlights of the ongoing construction projects taking place across the district through two voter-approved bond questions, allowing SoWashCo Schools to begin construction projects at 15 schools over the course of 5 years.

 

Park High School 

  • A temporary fence was installed between Park High School and Crestview Elementary for site improvements
  • Demolition of the lecture hall was completed and is on track to open before school resumes
  • Interior classroom demo and concrete preparations are in process
  • Freezer demolition began
  • Next Steps: Continuing interior demolition, utilities and MEP rough-ins

 

 demolitions

Woodbury High School 

  • A temporary fence was installed 
  • Storage spaces under the stairs were completed
  • Temporary walls were set up
  • Pool demolition began
  • The administrative office moved to the choir room
  • Next Steps: New trainer room demolition started to be completed

 

 

demolition  demolition 

East Ridge High School 

  • Interior demo began is on track
  • Parking lot work South of the Job trailer began
  • New temporary entrance installation began 
  • Track surface protection completed
  • Next Steps: The new pod's carpet and furniture is to be installed in August

 

A building on the side of a road

AI-generated content may be incorrect.

A road with a building and trees

AI-generated content may be incorrect.

Oltman Middle School 

  • Foundation walls were poured for the storm shelter
  • The temporary wall in the cafeteria was completed
  • The kitchen's temporary wall began
  • The parent drop off road is now shut down
  • Activities entrance (Door 30) is shut down for the summer
  • Curtain wall demo at the cafeteria started last week
  • Next Steps: The temporary wall in the locker bay is to begin

 

 

new windows   A construction site with a building and a road

Woodbury Middle School  

  • The new bus lane road is in process and is scheduled to be completed by mid-summer
  • Bleacher demolition in the pool began
  • Wrestling room and garage demolition continues
  • The new fiber line is scheduled to be spliced in on June 17 at  6 p.m.
  • Next Steps: Grading, road work and more interior work

 

 

A yellow construction vehicle on dirt

AI-generated content may be incorrect.   A construction site with many pipes

AI-generated content may be incorrect.

Cottage Grove Middle School

  • Site fencing to be installed mid-July

Lake Middle School

  • Site fencing to be installed mid-July