Skip To Main Content

Construction Update - September 2025

Construction Update - September 2025

Here are a few Fall 2025 highlights of the ongoing construction projects taking place across the district through two voter-approved bond questions, allowing SoWashCo Schools to begin construction projects at 15 schools over the course of 5 years.

Park High School 

  • Bus road through the Crestview lot open for afternoon traffic
  • The lecture hall and the new admin area are now in use with temporary tables
  • New furniture to be delivered before MEA
  • New footings for the addition are complete
  • New nurse office is up and running. 
  • The temporary greeter desk is operational
Park high school entrance

Woodbury High School 

  • Structural wall was completed for the addition
  • Underground utilities were completed
  • Door 16 is up and running

 

Woodbury Construction zone


 

East Ridge High School 

  • New pod carpet and hard furniture has been installed
    • Soft furniture scheduled to be delivered in October
  • Footings started in Q,R and S for the new addition
  • Fiber Splice tentatively scheduled for later this month
  • Parking lot work is complete
  • Marching band lines complete in the staff parking lot
  • Area L scheduled for completion this month
East Ridge Construction

Oltman Middle School 

  • New Parent drop-off and pick-up lane has been established
  • Curb and gutter near bus turnaround scheduled for later this month
  • Deep underground utilities in Area C have been completed 
  • Crane will be back onsite later this month for more precast work

 

 

OMS fall construction


Woodbury Middle School  

  • The new bus lane road was completed prior to school start
  • Retention area landscaping to start on 9/15
  • Prep work for new grass in fields between schools to start later this month
  • New doors have been cut into the Multipurpose and storage rooms
  • New floor in the new storage room to start this month
  • Bus lane signage to be installed this month
  • Concrete pour for the back of the school is scheduled later this month
  • Infills were completed in the garage and orchestra rooms
  • Exterior doors were cut in the new garage area

 

Woodbury Middle School construction

Cottage Grove Middle School

  • Tree removal began
  • Site clearing for the new addition began
  • Excavations for footings to start this month
  • Footings to be poured later this month
CGMS construction map

Lake Middle School

  • Tree removal was completed
  • Site clearing started this week for the new addition
  • Excavations for footings to start this month
  • Footings to be poured later this month
  • Pioneer and Lake roundabout is open
LMS construction map