Construction Update - December 2025

Construction Update - December 2025

Here are a few Fall 2025 highlights of the ongoing construction projects taking place across the district through two voter-approved bond questions, allowing SoWashCo Schools to begin construction projects at 15 schools over the course of 5 years.

 

Park High School 

  • Phase 2 is closing out this week
    • Area G and H furniture being installed this week
    • Punch items ongoing
  • Slab pour in addition is on track and has started
    • Kitchen slab has been poured
    • Prep work for storm shelter has begun
  • Roofing is in process.
    • They are currently wrapping up storm shelter portion of the roof
  • Fire proofing has begun in Area E
  • Framing in Area N has begun
park high school draft construction

Woodbury High School 

  • Area A
    • Temp enclosures have been installed
    • Roof demo complete
    • Curtain wall to be installed mid January
  • Area B
    • Learning stairs foundation poured
    • Roof blocking scheduled for 12/11
    • Roofing tentatively scheduled for next week (weather permitting)
  • Power shut down is scheduled for 12/29 and 12/30
  • Area C
    • Masons are continuing in this area
woodbury construction zone details

East Ridge High School 

  • Area T
    • This area is underway again
    • Backfilling this week
    • Precast panels to arrive on 12/15
  • Area Q
    • Precast team onsite this week for final touches in this area
    • Finalizing roof in this area this week
  • Area R
    • Plank installed
    • Detail welding this week
    • Joists installed this week as well
  • Area S
    • Steel delivered today
    • Plank to be set on 12/15
East Ridge Construction

Oltman Middle School 

  • Area C
    • Angle iron arrived last week
    • MEPS roughing in this week
    • Widows at storm shelter started today and finish 12/12
    • Roofing to start on 12/15
  • Area D
    • Brick veneer in process
    • Footings and foundation walls started today
      • Backfill to follow
    • The rest of the steel to start mid week this week
    • Enclosing this area this week
  • Area A and B
    • Columns and beams to be installed this week
    • Veneer in process
    • Interior lintels to be installed late this week
    • Temp enclosure in in process in this area
    • Slab prep work in complete
      • Slab pour on track
Oltman Construction

 

Woodbury Middle School  

  • Multipurpose space (Area C)
    • Floor leveling installed
    • Wall prep completed last week
    • Painting completing this week
    • Flooring install scheduled for 12/15
  • AHU #5 and #9 scheduled for start up on 12/12
  • Orchestra
    • Furniture to arrive 12/15
    • Final Clean schedule for 12/15
  • Punch walk for Area B and C scheduled for 12/18
woodbury construction zone details

Cottage Grove Middle School

  • Roofing completed last week
  • Air barrier completed last week
  • Exterior insulation in process
  • Interior slab on grade pour today and tomorrow
  • Brick work starting this week
  • Interior walls starting later this week
Cottage Grove construction

 

Lake Middle School

  • Exterior Sheathing completed last week
  • Blocking installed last week
  • Air barrier started today
  • Terrazzo demo started last week in old vestibule
  • Roofing will complete this week
  • Exterior insulation is scheduled for late this week and early next
  • Slab on grade is scheduled for 12/15
  • Interior walls scheduled for late next week
Lake middle school construction