Construction Update - December 2025
Construction Update - December 2025
Here are a few Fall 2025 highlights of the ongoing construction projects taking place across the district through two voter-approved bond questions, allowing SoWashCo Schools to begin construction projects at 15 schools over the course of 5 years.
Park High School
- Phase 2 is closing out this week
- Area G and H furniture being installed this week
- Punch items ongoing
- Slab pour in addition is on track and has started
- Kitchen slab has been poured
- Prep work for storm shelter has begun
- Roofing is in process.
- They are currently wrapping up storm shelter portion of the roof
- Fire proofing has begun in Area E
- Framing in Area N has begun

Woodbury High School
- Area A
- Temp enclosures have been installed
- Roof demo complete
- Curtain wall to be installed mid January
- Area B
- Learning stairs foundation poured
- Roof blocking scheduled for 12/11
- Roofing tentatively scheduled for next week (weather permitting)
- Power shut down is scheduled for 12/29 and 12/30
- Area C
- Masons are continuing in this area

East Ridge High School
- Area T
- This area is underway again
- Backfilling this week
- Precast panels to arrive on 12/15
- Area Q
- Precast team onsite this week for final touches in this area
- Finalizing roof in this area this week
- Area R
- Plank installed
- Detail welding this week
- Joists installed this week as well
- Area S
- Steel delivered today
- Plank to be set on 12/15

Oltman Middle School
- Area C
- Angle iron arrived last week
- MEPS roughing in this week
- Widows at storm shelter started today and finish 12/12
- Roofing to start on 12/15
- Area D
- Brick veneer in process
- Footings and foundation walls started today
- Backfill to follow
- The rest of the steel to start mid week this week
- Enclosing this area this week
- Area A and B
- Columns and beams to be installed this week
- Veneer in process
- Interior lintels to be installed late this week
- Temp enclosure in in process in this area
- Slab prep work in complete
- Slab pour on track

Woodbury Middle School
- Multipurpose space (Area C)
- Floor leveling installed
- Wall prep completed last week
- Painting completing this week
- Flooring install scheduled for 12/15
- AHU #5 and #9 scheduled for start up on 12/12
- Orchestra
- Furniture to arrive 12/15
- Final Clean schedule for 12/15
- Punch walk for Area B and C scheduled for 12/18

Cottage Grove Middle School
- Roofing completed last week
- Air barrier completed last week
- Exterior insulation in process
- Interior slab on grade pour today and tomorrow
- Brick work starting this week
- Interior walls starting later this week

Lake Middle School
- Exterior Sheathing completed last week
- Blocking installed last week
- Air barrier started today
- Terrazzo demo started last week in old vestibule
- Roofing will complete this week
- Exterior insulation is scheduled for late this week and early next
- Slab on grade is scheduled for 12/15
- Interior walls scheduled for late next week

